DELTA LTL2000 Retrometer 41
Status after first Zero
After executing a ZERO function the status will look
like this.
It shows that the Zero measurement has been
executed and when this was done.
No calibration has been done yet.
The values recorded during the zero measurement,
the system leak, the dark signal and the offset signal
are listed.
The voltage conditions during the zero measurement
are shown:
Battery voltage measured when the lamp is on, the
voltage with the lamp off and finally the PMT voltage:
It can be seen that the data from the zero measure-
ment went into the Test Log.